How to Compare Adsorbent Quotations Line by Line
Two quotations for the "same" molecular sieve can differ by a third once price basis, packaging, lead time and documents are counted — and the cheaper headline price is often the more expensive order.
This guide shows how to compare adsorbent quotations line by line: align the specification first, put every price on the same basis, check the five lines every quotation must contain, and add the hidden costs before you sign.
Step 1: Align the Specification Before You Compare Prices
A quotation is only comparable when it answers the same question. Different grades, bead sizes or packaging produce different prices — and a price you cannot compare is a price you cannot use.
Before you compare anything, check that every supplier quoted the same specification: product type and grade — 3A, 4A, 5A or 13X molecular sieve, or the activated alumina grade for your dryer — bead size (1.6–2.5 mm or 3–5 mm), quantity, packaging and destination. Molecular sieves are sold mainly as spherical beads; pellets are available on request, so confirm the form in writing — a bead price and a pellet price are not the same product. If one quotation is for 3–5 mm beads and another for 1.6–2.5 mm beads, stop comparing and ask both suppliers to quote the size you actually need. The same applies to quantity: a price per tonne at 20 tonnes is not the price at 2 tonnes, because freight and handling per tonne change with quantity.
Step 2: Put Every Price on the Same Basis — EXW vs FOB vs CIF
The most common reason two quotations look different is that they are not prices for the same thing: one covers the material at the plant, the other already includes freight to your port.
We quote EXW Zibo: the price covers the material at our plant, and freight is calculated per order, because inland freight to the port varies with quantity. A FOB price adds export handling and loading at the port of shipment; a CIF price adds ocean freight and insurance to your destination port as well. None of these is wrong — but they cannot be compared directly. Ask every supplier for the EXW price alongside any FOB or CIF figure, so material cost and freight cost stay separate and you can see which supplier is actually cheaper on the material. Then compare freight on the same route and the same quantity: a CIF price that looks low may simply assume a slower vessel or a different port.
| Price basis | What it covers | What to ask |
|---|---|---|
| EXW | Material at the supplier's plant | Add your own freight to compare like with like |
| FOB | Material, export handling and loading at the port of shipment | Confirm the port and what handling includes |
| CIF | Material, ocean freight and insurance to your destination port | Confirm the port, transit time and insurance cover |
Step 3: Check the Five Lines Every Quotation Must Contain
A complete quotation answers five questions. If any line is missing, the price is not final — it is a starting point for extra charges.
First, grade and bead size, confirmed in writing. Second, quantity and unit — tonnes or kilograms, and whether the price is per tonne or per bag. Third, packaging: 25 kg bags, 150 kg steel drums or bulk bags, and whether packaging is included in the price or charged separately. Fourth, lead time: bulk orders run 15–25 days, so a quotation without a lead time cannot be planned against a shutdown or a bed change-out. Fifth, documents: a technical datasheet and a batch certificate of analysis (COA) with the shipment — without a COA, the batch cannot be verified on arrival. If a quotation leaves any of these out, ask for it in writing before you compare. A supplier that answers clearly at the quotation stage is the supplier that answers clearly when a delivery goes wrong.
| Line | What good looks like | Red flag |
|---|---|---|
| Grade and size | Grade and bead size stated in mm | "Molecular sieve" with no grade |
| Quantity and unit | Tonnes or kg, price per tonne stated | A price with no unit |
| Packaging | 25 kg bags, 150 kg drums or bulk bags, included in the price | Packaging charged separately, unstated |
| Lead time | 15–25 days for bulk orders, stated in writing | No lead time given |
| Documents | Datasheet and batch COA with the shipment | COA only "on request" or not mentioned |
Step 4: Add the Hidden Costs Before You Choose
The headline price is rarely the landed cost. Four costs hide outside the quotation — and they decide which offer is actually cheapest.
Freight and port charges: on an EXW quotation, add inland freight, export handling and ocean freight yourself, on the same route and quantity for every supplier. Payment terms: a quotation that requires full payment in advance costs more in working capital and risk than one with payment against documents — compare the terms, not just the price. Re-testing: if a delivery arrives without a batch COA, you pay for your own laboratory test before the material goes into the bed, and a failed test costs a shutdown. Repackaging and handling: 25 kg bags suit manual loading; 150 kg steel drums need a drum unloader; bulk bags need a forklift and a dry store. Packaging that does not fit your site becomes a handling cost — or a damaged batch. Add these four lines to every quotation and the ranking often changes: the cheapest material price with the most expensive freight and no COA is rarely the cheapest order.
Step 5: The Ten-Minute Comparison Routine
Once the quotations are aligned, the comparison itself takes ten minutes — one table, one pass, one decision.
Build one table with one column per supplier and one row per line: grade and size, quantity and unit, EXW price, freight, packaging, lead time, documents and payment terms. Fill it from the quotations, not from memory, and leave a row blank where a supplier did not answer — a blank row is a question, not a zero. Then read the table twice: once for the lowest landed cost, once for the lowest risk. If the cheapest landed cost comes from a supplier with no COA, no stated lead time and payment in advance, the second reading should win. Keep the table with the purchase order: when the delivery arrives, it is the checklist you verify against — grade, size, packaging and the batch number on the COA — before the material goes into the bed.
| Line to compare | Where to find it | What to write down |
|---|---|---|
| EXW price | Price line of the quotation | Price per tonne, material only |
| Freight to your port | FOB/CIF figure, or your own freight quote | Same route and quantity for all |
| Packaging | Packaging line | Bag, drum or bulk bag; included or extra |
| Lead time | Validity and delivery terms | Days from order to shipment |
| COA and datasheet | Documents line | Batch COA with shipment, yes or no |
| Payment terms | Payment line | Advance, against documents, or credit |
| Total landed cost | Your calculation, not the supplier's | Material + freight + handling |
For the numbers behind this guide, see the molecular sieve product page, our RFQ checklist and how to read a COA before you buy.
Frequently Asked Questions
Why do two quotations for the same molecular sieve differ so much?
Because they rarely quote the same thing: different bead size, different packaging, a different price basis (EXW vs FOB vs CIF) and different documents. Align the specification first, then compare.
Should I compare the EXW price or the CIF price?
Both, separately. Compare EXW prices to see which supplier is cheaper on the material, then compare freight on the same route and quantity. A low CIF price can hide expensive material behind cheap freight.
What if a quotation has no lead time?
Ask for it in writing before you compare. Bulk orders run 15–25 days; without a lead time you cannot plan a shutdown or a bed change-out, and a fast price with no date is not a fast delivery.
Is the cheapest quotation the best one?
Only if the whole offer is cheapest: material, freight, packaging, documents and payment terms together. A quotation without a batch COA, or with payment in advance, can cost more than the next-priced offer once testing and risk are added.
Ready to compare on a like-for-like basis? Send us the product type, grade, bead size, quantity and destination — our engineers will confirm the grade and send an EXW quotation you can compare line by line: barry@okkinc.com.
Get a Quote
Tell us the product, grade and quantity. We reply within 12 hours with EXW pricing and lead time.
- ✓ COA and technical datasheet with every shipment
- ✓ EXW pricing — freight calculated per order
- ✓ Engineering consultation on grade selection and loading